This was a brand new school built on an environmentally sensitive piece of land. Due to Army Core Permit delayed this project by two months. Shortening the overall project schedule to 12 months.

 

After carefully prepping the site and installing over 4’ of fill; as well as Vibro replacement, we were ready to go vertical.  The school consisted of classrooms, computer and science labs, a media center, kitchen/cafeteria, stand alone gymnasium, music, and band rooms.  Our original contract scheduled 14 months for completion.  We completed this project in 10 months including site work.

Project Size: 164,225 sqft. | Start Date: 04.2011 | Completion Date: 07.2012

Dual Site Projects require a specific skill set in regards to scheduling and coordination.  When faced with a dual-site, Gulfpoint Construction scheduling, is not only precise, but it is well understood by all trades.

 

We established each trade schedule with them and pointed out the crucial areas of conflicts.  We had to meet daily with the trades to make sure we kept the flow of this project running smoothly.  If we lost our momentum, frustration occurs and quality slips.  As a team, we made sure all trades kept working without losing time due to improper coordination. The school consisted of classrooms, computer and science labs, a media center, kitchen and cafeteria, stand-alone gymnasium, music, and band rooms.  

Project Size: 179,000 sqft. | Start Date: 03.2006 | Completion Date: 04.2008